STANFORD HOUSE
Project overview
Stanford House in Floral Street, Covent Garden is a Grade II listed building with commercial and residential occupants. Our brief was to refurbish, revive and renew the complete common parts from ground to 5th floor including lift car, lift lobbies and reception. The works were carried out at a variety of times throughout the day, night, and weekends to eradicate any disruption to the tenants. Health & Saftey was a paramount concern and all tenants were kept constantly informed on the day to day status of works through direct communication, notices and site signage.
Key Objectives
Many aspects of the work had to be completed within a very specific time frame to maintain fire escape routes. All plant and materials were delivered and taken away on a daily basis as there were no storage areas. Site cleanliness was maintained at all times.
Specifications
- New Lighting
- Fire strategy improvements
- New lift lobby ceilings
- Lift car refurbishment
- Decorations
- New manifestations
- Corporate Signage
- Bespoke joinery
- Solid wood flooring rejuvenation
- New carpet & stair nosings
- New entrance matting
- New entrance ramp & pavement light repairs
- Cleaning of external facade
- CLIENT ING Real Estate
- Contract
AdministartorTrident BC - ContractJCT Minor Works
- Value£50k
- Duration4 Weeks
- CATEGORY Case Studies